Hi there All,
We’ll preserve this one brief and candy! Many components have arrived and extra are scheduled. To this point the time estimates and assumptions made within the earlier replace are nonetheless on monitor.
-
Full manufacturing cargo of recent heating ingredient gaskets have arrived on Might 17, 2023
-
The primary 300 filters for the ability plug have arrived on Might 17, 2023
-
Full manufacturing cargo of up to date bent fill tubes shipped on Might 18, 2023
-
40 again panels with the up to date energy outlet cutout shipped on Might 18, 2023
-
60 again panels are anticipated to ship on a weekly foundation
-
We’ll pause right here for a second as a result of it is a key replace. As soon as now we have these 40 again panels in hand, we will lastly end the entire meeting of 40 machines!
Extra updates:
-
Molded pulp packaging inserts with outer packaging will begin delivery subsequent week.
-
We estimate we are going to obtain 50 models on this first batch.
-
-
Paid last bill for EMI/EMC testing, ready for reviews to be despatched to us. That is the one certification needed for home shipments.
-
Security testing continues to be ongoing with one remaining check then documentation (needed for delivery exterior of the US).
-
We’re seeking to convey on one other Meeting Technician. See right here for extra particulars https://www.odysseyespresso.com/join-us Please attain out to us when you’re !
Thanks all once more in your persistence. A lot of you have got reached out to us with variety phrases about our transparency and dedication to delivering a top quality product. We learn all of them! We all know we’ve missed our goal quite a lot of occasions, however we expect we’re lastly seeing the tip of the tunnel.
Accomplished Piston Assemblies. All of them get individually wrapped now to keep away from the danger of scratching. [/caption]
LOTS of components got here in final week. There are all of the remaining welded boilers and sheet steel components.